Jesup-Offerman 115kV Line

Jesup-Offerman 115kV Line

Jesup-Offerman 115kV Line

Transmission

Project Type: Transmission

Scope: Setting new concrete poles and reconducting 31 total miles of 115kV transmission line.

Location: Southern Georgia

Start Date: October 2025

Completion Date: In Progress

Sumter Utilities crews are hard at work on a major transmission upgrade along the Jesup-Offerman transmission line, a 31-mile project spanning southern Georgia.  The scope of the project calls for setting new concrete poles and reconducting 115kV wire to keep pace with growing electrical demand in the region. Work began in late October 2025 and has continued steadily since, with two dedicated crews assigned to the job — crew 245, led by Foreman David Haire, and crew 835, led by Foreman Kyler Lee.

The pole replacement process has required careful sequencing to keep both the transmission and distribution systems safe throughout construction. New concrete poles, weighing just under 40,000 pounds apiece, have been set using a 200-foot crane, with local traffic control and police coordinating lane closures on the adjacent highways during each lift.

As the project has progressed, crews have kept up with routine safety requirements, including a scheduled glove changeout at the laydown yard, where rubber goods are inspected and swapped out every six months. Every morning starts with a JTSA to keep the crew on the same page. Even the neighborhood dog shows up hoping for a snack (pictured in gallery above) — but hopefully he picks up a lesson in safety along the way too!

This project remains in progress.

Dairy-Holland Park 138kV TL Modifications

Dairy-Holland Park 138kV TL Modifications

Dairy-Holland Park 138kV TL Modifications

Transmission

Project Type: Transmission

Scope: Emergency transmission line repairs and upgrades along navigable waterway.

Location: Melbourne, Florida (Indian River Waterway)

Client: Irby Construction, and Florida Power & Light

Start Date: October 2024

Completion Date:
December 2024

Sumter Utilities served as a subcontractor for Irby Construction on this emergency repair project along the Indian River Waterway in Melbourne, Florida. The project involved specialized barge-based operations to access and upgrade 17 transmission structure locations on a line originally constructed in 1983.

Two dedicated Sumter crews performed time and materials (T&M) work to implement several critical upgrades. The scope included replacing outdated bell insulators with modern polymer alternatives, installing new through bolts to enhance structural integrity, and adding reflective strips essential for safety in navigable waterways. The team also reinforced existing infrastructure by installing new down guy wires and guy plate attachments for brace poles. Additionally, crews installed steel bands to secure concrete poles to their concrete pier foundations, ensuring long-term stability in the challenging waterway environment.

The barge-based approach allowed our teams to access these difficult locations while minimizing environmental impact to the sensitive Indian River ecosystem. Through careful coordination and specialized equipment, Sumter successfully completed these essential reliability improvements to maintain power delivery in the Melbourne area.

Square D-Hopkins 115kV Transmission Line Rebuild

Square D-Hopkins 115kV Transmission Line Rebuild

Square D-Hopkins 115kV Transmission Line Rebuild

Transmission

Project Type: Transmission

Scope: 4.62-mile transmission line rebuild (Wood H-Frame to Single Pole Steel)

Location: Hopkins, SC

Client: Dominion Energy South Carolina (DESC)

Start Date: June 2024

Completion Date: October 2024

Sumter Utilities served as the prime contractor for this 4.62-mile transmission line rebuild, converting wood H-frame structures to single pole steel for Dominion Energy South Carolina. The project required extensive environmental protection measures across delineated wetlands.

When estimating this project, Sumter had a choice: pay a subcontractor to properly manage the matting, or leverage partnerships within Quanta to self-perform the matting element of the job and reduce expenses. Ultimately, Sumter stepped up to new challenges, and managed the installation of 5,300 specialized timber mats with help from B&N Clearing, a sister company. Crews handled all matting operations including hauling, installation, repositioning, and removal with support from substation teams and Lee Electrical.

Ultimately, Sumter finished the project well below budget, and with a new skillset to add to our resume. This infrastructure modernization will improve power reliability for Dominion Energy while demonstrating Sumter’s commitment to environmental responsibility in sensitive ecological areas.

Pepsi Frito Lay Distribution Center EV Charger Installation

Pepsi Frito Lay Distribution Center EV Charger Installation

Pepsi Frito Lay Distribution Center EV Charger Installation

Renewable Energy

Project Type: Renewable Energy

Scope: Installation of 61 dual port EV chargers, two 120kW fast chargers and supporting panels to “electrify” the Pepsi Frito Lay transit fleet.

Location: Richmond, Virginia

Client:Pepsi Frito Lay / QISG

Start Date: November 2023

Completion Date: September 2024

In an effort to enhance sustainability in the market, Pepsi Frito Lay sought to electrify their transit trucks used for distributing products to local market customers. This major change required a substantial upgrade to their distribution facility in Richmond, Virginia with the addition of EV charging stations.

In conjunction with Energy Services West / QISG, and their engineering partner, Sumter Utilities substation crews installed 61 ATOM Power dual port EV chargers, an additional two 120kW fast chargers, and the supporting ‘SMART’ Atom PURPL Panels.

The work required constant communication among crew members, and a little creativity in coordinating the work while the distribution facility remained fully operational. As the crew learned new techniques and tackled unfamiliar territory in the world of EV charging, they regularly worked to troubleshoot challenges that arose along the way.

Ultimately, the project was completed safely and without incident. Pepsi Frito Lay was very pleased with the work Sumter Utilities completed.

Clements Ferry Road Expansion

Clements Ferry Road Expansion

Clements Ferry Road Expansion

Overhead Distribution

Project Type: Overhead Distribution

Scope: Approximately five miles of overhead distribution line conversion and pole replacement

Location: Mount Pleasant,  South Carolina

Client: Dominion Energy Southeast (SC)

Start Date: Early 2018

Completion Date: Fall 2022

Outside of Charleston, South Carolina, the city of Mount Pleasant set out to widen Clements Ferry Road, a high-traffic roadway accomodating commuters in and out of Charleston. With the expansion of the road came upgrades to the accompanying infrastructure, including power lines.

The project required collaboration between road construction crews and contractors in various industries: water, sewer, gas, paving, and department of transportation, along with Sumter Utilities who was tasked with replacing more than 100 poles and wire.

With so many moving parts along a high-traffic area, clear communication, attention to detail, and coordination were critical. Sumter was assigned one point of contact to coordinate with other contractors to ensure that work could happen seamlessly. It was like a dance, where every move was choreographed in detail to avoid delays.

Sumter Utilities foreman spoke with other contractors on the job daily, sometimes even hourly. Three crews worked around rush hour traffic and other key players to ensure that the job was completed safely and on time.