Pepsi Frito Lay Distribution Center EV Charger Installation

Pepsi Frito Lay Distribution Center EV Charger Installation

Pepsi Frito Lay Distribution Center EV Charger Installation

Renewable Energy

Project Type: Renewable Energy

Scope: Installation of 61 dual port EV chargers, two 120kW fast chargers and supporting panels to “electrify” the Pepsi Frito Lay transit fleet.

Location: Richmond, Virginia

Client:Pepsi Frito Lay / QISG

Start Date: November 2023

Completion Date: September 2024

In an effort to enhance sustainability in the market, Pepsi Frito Lay sought to electrify their transit trucks used for distributing products to local market customers. This major change required a substantial upgrade to their distribution facility in Richmond, Virginia with the addition of EV charging stations.

In conjunction with Energy Services West / QISG, and their engineering partner, Sumter Utilities substation crews installed 61 ATOM Power dual port EV chargers, an additional two 120kW fast chargers, and the supporting ‘SMART’ Atom PURPL Panels.

The work required constant communication among crew members, and a little creativity in coordinating the work while the distribution facility remained fully operational. As the crew learned new techniques and tackled unfamiliar territory in the world of EV charging, they regularly worked to troubleshoot challenges that arose along the way.

Ultimately, the project was completed safely and without incident. Pepsi Frito Lay was very pleased with the work Sumter Utilities completed.

Solomon’s Island Conversion

Solomon’s Island Conversion

Solomon’s Island Conversion

Underground Distribution

Project Type: Underground Distribution

Scope: 2,000 ft of Overhead to Underground conversion

Location: Solomon’s Island, Maryland

Client: Southern Maryland Electric Cooperative

Start Date: 2021

Completion Date: May 2022

Sumter Utilities was contracted by Southern Maryland Electric Cooperative to complete a three-phase conversion of overhead distribution to underground distribution along Solomon’s Island Road, a popular tourist destination for the Baltimore-Washington Metro area. The distance stretches approximately 2,000 feet from the historic Lore Oyster House to Patuxent Avenue.

This project includes a complete turn-key solution for the conversion, including duct bank installation, primary and secondary cable installation, conversions and cut-overs, street light install, cable terminations, and restorations. The beginning of the project spans an open causeway, with the design including a carrier pipe over the 24 feet of waterway.

Together with our subcontracted partner, Southern Maryland Cable, Sumter Utilities is facing the challenges of a high water table, unstable soil, existing underground utilities, Maryland winter weather, and as many have seen in 2021, material procurement. The supply chain issues and the intricacies of this project have given plenty of obstacles to overcome, but the team is scheduled to complete the project on time in May of 2022.